Latest News
28th November 2022
The Section 36 application for the Kirkton Energy Park has been submitted to the Scottish Government Energy Consents Unit.
Read more »
9th March 2022
Wind2 will be holding an online 'Virtual' Public Exhibition on 16th March where the latest proposals for the Kirkton Wind Farm will be presented.
Read more »
17th September 2021
Wind2 will be holding a Public Exhibition on 6th October in Strathy Village Hall where the draft proposals for the Kirkton Wind Farm will be presented.
Read more »
18th August 2021
Planning permission has been granted by The Highland Council for erection of a temporary 80m guyed meteorological mast on land at Kirkton Farm.
Read more »
1st July 2021
Wind2 have submitted an addendum to the Kirkton Wind Farm Scoping Report to the Scottish Government Energy Consent Unit (ECU), following extension of the project site boundary to include additional land to the south on Upper Bighouse farm.
Read more »
7th June 2021
The Scottish Government Energy Consent Unit (ECU) have published the Scoping Opinion for Kirkton Wind Farm on behalf of Scottish Ministers.
Read more »
22nd March 2021
Wind2 have requested a formal Scoping Opinion from the Scottish Government Energy Consents Unit (ECU).
Read more »